Migrating Siemens S7-1200 G1 to S7-1200 G2

Enhanced Control Solutions · · 8 min read

Siemens began phasing out the first-generation S7-1200 on 1 November 2026. New G1 units should be ordered by 30 September 2027 (Siemens’ sources give 1 October and 31 October as the end of new-part supply), and spares are planned until about 2036. Our S7-1200 G1 end-of-life summary covers the dates and the spares-or-migrate decision.

The successor is the SIMATIC S7-1200 G2. It stays in TIA Portal and uses the same programming model, so this is a much smaller step than an S7-300 to S7-1500 migration. It is still not a drop-in replacement: the hardware, terminals and some functions have changed. This guide sets out what changes, what Siemens’ tools do, and what to check.

Choosing the G2 CPU

Siemens’ migration overview gives a direct G2 successor for each 1212C, 1214C, 1212FC and 1214FC, matched by power supply and output type:

G1 CPU G1 article number G2 article number
CPU 1212C DC/DC/DC 6ES7212-1AE40-0XB0 6ES7212-1AG50-0XB0
CPU 1212C AC/DC/relay 6ES7212-1BE40-0XB0 6ES7212-1BG50-0XB0
CPU 1212C DC/DC/relay 6ES7212-1HE40-0XB0 6ES7212-1HG50-0XB0
CPU 1214C DC/DC/DC 6ES7214-1AG40-0XB0 6ES7214-1AH50-0XB0
CPU 1214C AC/DC/relay 6ES7214-1BG40-0XB0 6ES7214-1BH50-0XB0
CPU 1214C DC/DC/relay 6ES7214-1HG40-0XB0 6ES7214-1HH50-0XB0
CPU 1212FC DC/DC/DC 6ES7212-1AF40-0XB0 6ES7212-1AF50-0XB0
CPU 1212FC DC/DC/relay 6ES7212-1HF40-0XB0 6ES7212-1HF50-0XB0
CPU 1214FC DC/DC/DC 6ES7214-1AF40-0XB0 6ES7214-1AF50-0XB0
CPU 1214FC DC/DC/relay 6ES7214-1HF40-0XB0 6ES7214-1HF50-0XB0

The 1211C, 1215C, 1217C and 1215FC have no listed G2 successor. Siemens’ overview compares the 1211C with the G2 1212C, and the 1215C and 1217C class with the G2 1214C. Check I/O count, memory and analogue requirements before choosing; a 1215C or 1217C application may need extra modules or a different controller.

The G2 has more memory than the G1. Siemens gives 150 or 200 kB of program memory and 500 kB of data memory for the G2 1212, against 75 to 150 kB in total for the G1. It also has two PROFINET ports on every CPU, supports up to 31 PROFINET devices instead of 16, and adds PROFINET IRT, NFC and DHCP/DNS.

Modules and signal boards

Siemens says “most of the known modules” from the S7-1200 family are available for G2. Its overview lists G2 successors for the common digital and analogue signal modules (SM 1221, 1222, 1223, 1231, 1232, 1233, plus RTD and thermocouple versions), the signal boards, the CB 1241 and CM 1241 serial modules, the CP 1243-1, the CSM 1277 switch, the SM 1226 fail-safe module and the PM 1207 power supply.

Some G1 modules have no G2 version yet. Siemens lists IO-Link, energy meter, PROFIBUS, CAN and weighing modules as still in development. A machine that depends on one of those needs a workaround or has to wait.

Siemens’ overview does not say that G1 modules can be fitted to a G2 CPU. Plan to replace the modules with the CPU. The G2 1212C has one signal board slot and the 1214C two, so check boards against slots.

Hardware changes

  • Smaller CPUs. The G2 CPU 1212C is 70 mm wide (G1: 90 mm) and the 1214C is 80 mm (G1: 110 mm). Installation depth and clearances have increased.
  • Connectors move. The PROFINET ports are on the top of the CPU and the power connector is on the bottom. Cable routing in the panel usually needs changing.
  • Push-in terminals replace screw terminals. Existing wiring will need re-terminating, and ferrules checking.
  • Lower temperature limits in some layouts. With all I/O active, Siemens gives 40°C for the G2 against 50°C (horizontal) or 45°C (vertical) for the G1. A G1 in a warm panel that relied on the higher limit needs checking.

Converting the program

The G2 needs TIA Portal V20 or later. Siemens provides a TIA Portal add-in with two parts: a Migration Checker, which checks the project for compatibility, and a Migration Tool, which migrates hardware and software automatically and produces a log of issues and recommendations.

Siemens says some manual steps “may still need to be performed, depending on the project content”. Its manual checklist is the best guide to what to review after the tool has run:

  • CPU selection and module properties, including partner ports and IP addresses
  • program blocks, and any blocks the G2 does not support
  • technology objects, such as motion axes and PID
  • PLC tag tables, user-defined data types, and trace, watch and force tables
  • security settings
  • a full compile, with every error and warning resolved.

Functions that change:

  • Web server. Standard web pages use a new interface. User-defined web pages built with AWP commands are not supported on the G2; Siemens replaces them with the Web API. Any custom web page needs rebuilding.
  • Configuration Control and Copy Protection were listed in Siemens’ overview as planned for the end of 2026. Check current availability if a project uses either.
  • Fail-safe CPUs. The 1212FC and 1214FC have G2 successors, but the overview does not describe safety program migration. Treat a safety program change as a safety change, with the validation that requires.

Before you start

  1. Back up every S7-1200 program and confirm it matches what is running, with the TIA Portal version it was built in.
  2. List every CPU, module and signal board by article number and firmware, and flag any with no G2 version yet.
  3. Run Siemens’ Migration Checker on each project before committing to a plan.
  4. Check the panel: space, cable routing to the new port positions, terminal changes and temperature.
  5. Rebuild custom web pages and recheck HMI and third-party communication against the converted project.
  6. Bench test, then test on the machine, including start-up, shutdown, alarms, recovery after a power cycle, and any safety functions.

How ECS approaches it

Most sites have S7-1200s on machines from several different builders, often with the only copy of the program on the CPU itself. A Capture audit backs up every reachable S7-1200, records each CPU and module by article number and firmware, and flags what is in phase-out, so the spares order and the migration plan are both built on what is installed. The converted projects, versions and cables are then held in Command Centre.

We carry out conversions, panel modifications and commissioning in-house as part of our automation projects, usually around planned stops. If a G1 fails before the plan is in place, emergency support is the first call.

Sources

Lifecycle dates and module availability change. Check a specific article number on Siemens’ site before buying or planning around it.